Current Status: April 2022
- The Virginia Department of Transportation (VDOT) approved a design waiver for the buffer strip width at intersection approaches and right turn lanes.
- For the next several weeks, the design team will continue developing 60% design plans and incorporating additional field survey information into the design.
- In February, the Board of Supervisors endorsed the project's major design elements.
- Project design is estimated to be completed in winter 2023.