Evergreen Mills Road and Watson Road Safety Audit

Current Transportation and Capital Projects The original category was published from July 2, 2019 1:21 PM to July 2, 2019 1:21 PM

Aug 05

[ARCHIVED] Contractor Bidding is Underway for Lovettsville Community Center Construction

The original item was published from August 5, 2020 2:22 PM to August 5, 2020 2:48 PM

An invitation for bid for a general contractor to complete the construction of the new Lovettsville community center was issued on August 4, 2020. View the bid on the Loudoun County Department of Procurement’s bid posting page for details.

Phase one of the original construction schedule was completed in June 2020, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot. The remaining four phases are delayed until a general contractor can be procured.

Construction is estimated to resume in late 2020.

The Lovettsville Community Center project will design and construct a new community center building in the Town of Lovettsville, replacing the existing building. The new community center will be over 15,000 square feet and will have a full-size gymnasium, five classrooms, a multipurpose room, a kitchen, administrative offices, meeting space and storage areas. The project also includes a 600-square-foot addition and renovation to the existing 1,200-square-foot Pool House.

For more information about the Lovettsville Community Center project, visit the project page.

Aug 05

[ARCHIVED] Contractor Bidding is Underway for Lovettsville Community Center Construction

The original item was published from August 5, 2020 2:22 PM to August 5, 2020 2:48 PM

An invitation for bid for a general contractor to complete the construction of the new Lovettsville community center was issued on August 4, 2020. View the bid on the Loudoun County Department of Procurement’s bid posting page for details.

Phase one of the original construction schedule was completed in June 2020, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot. The remaining four phases are delayed until a general contractor can be procured.

Construction is estimated to resume in late 2020.

The Lovettsville Community Center project will design and construct a new community center building in the Town of Lovettsville, replacing the existing building. The new community center will be over 15,000 square feet and will have a full-size gymnasium, five classrooms, a multipurpose room, a kitchen, administrative offices, meeting space and storage areas. The project also includes a 600-square-foot addition and renovation to the existing 1,200-square-foot Pool House.

For more information about the Lovettsville Community Center project, visit the project page.

Nov 07

[ARCHIVED] Phase 1 of the Lovettsville Community Center to be Completed in November

The original item was published from November 7, 2019 9:22 AM to November 7, 2019 9:27 AM

In November, work for Phase 1 of the Lovettsville Community Center wraps up with the completion of the gravel parking lot and geothermal well. Meridian Construction Co., Inc., Loudoun County’s general contractor, will begin the transition to Phase 2 at the end of the month.

Construction Phase 1 Update:
  • Work to establish a sediment basin and riser structure has been completed. 
  • Excavation, installation and back fill of the 18 inch reinforced concrete storm pipe is completed. 
  • Grading and gravel placement for the parking lot will be completed by the end of November.
  • The subcontractor is progressing with drilling for the geothermal well and expects to finish by the end of November.
For more information visit the Lovettsville Community Center project page.