Stormwater and Sidewalk Work on Church Street and Cornwall Street to Begin March 14

Posted on March 14, 2023 at 4:40 PM by Heidi Kellum

As part of Loudoun County’s Courthouse Complex Expansion project, construction crews will be performing stormwater and sidewalk work on Church Street from Cornwall Street to North Street, and on Cornwall Street from Slack Lane to Church Street in Leesburg in two phases from Tuesday, March 14 through Friday, March 31, 2023. Although no road closures are planned, residents are advised to use the Pennington Lot or other parking during this time. Drivers and pedestrians should use extra caution when traveling through these areas and follow all directions from the posted signs and road crews. Safe access to resident homes will be maintained and notices will be issued prior to the start of work.

March 14 through March 17 – Church Street Work Begins

From Tuesday, March 14 through Friday, March 17, work to install new curb, gutter and sidewalk is scheduled to take place from 7:00 a.m. until 5:00 p.m. on Church Street from Cornwall Street to North Street.

March 20 through March 31 – Cornwall Street Work Begins

From Monday, March 20 through Friday, March 31, work to install new curb, gutter and sidewalk is scheduled to take place from 7:00 a.m. until 5:00 p.m. on Cornwall Street from Slack Lane to Church Street.

Courthouse Complex Expansion Project

This construction is part of the Loudoun County Courthouse Complex expansion project that includes the design and construction of the new 92,000-square-foot Loudoun County District Courthouse and renovation of existing courts facilities, including new parking facilities. Work to install drywall, door frames and window glazing is complete on all levels. Permanent power for the new building has been established, and crews have installed the elevators and are painting interior walls.  

On the outside of the building, Church Street NE remains closed between Market and Cornwall Streets, which restricts vehicular and pedestrian traffic while crews work to complete the installation of dry utilities. Construction of an underground tunnel that connects the new courthouse to the existing courthouse has been completed. 

Planning is underway for the start of the existing courthouse renovation associated with the new tunnel.. The Loudoun County Courthouse Expansion project is expected to be complete and open to the public in 2023.
 
Visitors to the Loudoun County Courthouse will continue to have access to free parking throughout the duration of the project at the Pennington Lot and Pennington Garage which are  located approximately two blocks from the courthouse near the intersection of Church and North Streets, NE. View parking details and a map of the shuttle route and walking path in this flyer (PDF).

For more information about the new courthouse construction project, including contact information, and to sign up for email and text updates on the project, visit loudoun.gov/courts-expansion. For more information about the courts, visit loudoun.gov/courts.