Jul 08

Construction Continues at Hal and Berni Hanson Regional Park

Posted on July 8, 2021 at 12:23 PM by Heidi Kellum

Over the next several weeks, crews will continue to construct the various structures and features throughout Hal and Berni Hanson Regional Park, currently under construction on Evergreen Mills Road in Arcola. When completed, the park will feature 17 lighted athletic fields, including two artificial turf fields and one cricket field; five ponds; the historic Hanson House; an event lodge and nature center; a skate plaza and disc golf course; a splash pad and playground with inclusive features and over 75 acres of passive recreational space. 

Work on the park features currently includes the continued construction of boardwalks/piers, athletic field irrigation and lighting. Crews have begun underground plumbing rough-in at the splashpad and the installation of sod and sports netting posts at the athletic fields. 

At Hanson House, work on the stone chimney mortar joints and rough in for mechanical, electrical and plumbing has begun. Construction on the remaining structures throughout the park currently includes the installation of masonry walls, stonework, timber, siding and trim, windows, roofing, fire protection, interior painting, utility rough-in and ductwork. 

Ongoing work throughout the park includes the installation of underground utilities- earthwork, asphalt paving, curb and gutter installation, and the spreading of topsoil, mulch and seeding.

The Hal and Berni Hanson Regional Park project includes the design and construction of a new 257-acre regional park located on Evergreen Mills Road in Arcola, between the Brambleton and Willowsford communities. The park will be operated by the Loudoun County Department of Parks, Recreation and Community Services and is estimated for completion in spring of 2022.

For more information about the Hal and Berni Hanson Regional Park project, including updated site photos, visit the project page.

Jun 11

Construction Continues Throughout Hal and Berni Hanson Regional Park

Posted on June 11, 2021 at 8:58 AM by Heidi Kellum

Over the next several weeks, crews will continue to construct the various structures and features throughout Hal and Berni Hanson Regional Park, currently under construction on Evergreen Mills Road in Arcola. When completed, the park will feature 17 lighted athletic fields, including two artificial turf fields and one cricket field; five ponds; the historic Hanson House; an event lodge and nature center; a skate plaza and disc golf course; a splash pad and playground with inclusive features and over 75 acres of passive recreational space. 

Work to construct the various structures throughout the park currently includes the installation of concrete masonry walls, stonework, timber, siding and trim, windows, roofing, fire protection, utility rough-in, and ductwork. Where walls and ceilings are fully installed, interior painting has begun. At Hanson House, crews are demolishing the existing roof and chimney stonework in preparation for reconstruction. 

Crews will continue work on park features, including the construction of boardwalks/piers, mulching at trails, playground equipment installation, athletic field irrigation and lighting, and concrete formwork at the splashpad. Ongoing work throughout the park includes earthwork, asphalt paving, curb and gutter installation, and the spreading of topsoil, mulch and seeding. 

The Hal and Berni Hanson Regional Park project includes the design and construction of a new 257-acre regional park located on Evergreen Mills Road in Arcola, between the Brambleton and Willowsford communities. The park will be operated by the Loudoun County Department of Parks, Recreation and Community Services and is estimated for completion in spring of 2022.

For more information about the Hal and Berni Hanson Regional Park project, including updated site photos, visit the project page

May 11

Park Features Taking Shape at Hal and Berni Hanson Regional Park

Posted on May 11, 2021 at 11:13 AM by Heidi Kellum

Park features can be seen taking shape on the construction site for the Hal and Berni Hanson Regional Park, currently under construction on Evergreen Mills Road in Arcola. Last month, members of DTCI’s facilities construction group gave Blue Ridge District Supervisor Tony Buffington a tour of the park to view features and construction progress. The tour stopped at five areas throughout the massive 257-acre park. 

When complete, features of park will include 17 lighted athletic fields, including two artificial turf fields and one cricket field; five ponds; the historic Hanson House; an event lodge and nature center; a skate plaza and disc golf course; a splash pad and playground with inclusive features and over 75 acres of passive recreational space. The project is expected to be completed in the spring of 2022.

Work on park features currently includes the construction of boardwalks/piers, mulching at trails, installation of synthetic turf at Championship Fields, and fine grading at the splashpad. Crews continue to install the irrigation system and lighting at all athletic fields.

Construction of the structures located throughout the park currently includes installation of concrete masonry walls, stonework, columns and metal decking, roofing, fire protection, utility rough-in, and ductwork. At Hanson House, crews have begun framing the second floor and front porch and pouring front porch concrete. Work to install exterior siding continues.
Ongoing work throughout the park includes earthwork, asphalt paving, curb and gutter installation, and the spreading of topsoil and mulch.

The Hal and Berni Hanson Regional Park project includes the design and construction of a new 257-acre regional park located on Evergreen Mills Road in Arcola, between the Brambleton and Willowsford communities. The park will be operated by the Loudoun County Department of Parks, Recreation and Community Services. 