The original item was published from September 6, 2019 12:00 PM to September 9, 2019 4:50 PM
- The contract for construction has been awarded to Crisak, Inc. in the estimated amount of $8.945 million.
- Notice to Proceed with construction was issued on August 12, 2019.
- The groundbreaking took place on September 5, 2019. Read the news release.
For more information about the