Progress is Made on Phase 1 of the Lovettsville Community Center

Posted on October 10, 2019 at 11:10 AM by Heidi Kellum

Loudoun County’s general contractor, Meridian Construction Co., Inc., is making progress to complete Phase 1 of the Lovettsville Community Center construction project. In October, major earthwork for the gravel parking lot will be completed and a storm pipe will be installed.  

Construction Phase 1 Progress:

  • Site and structure demolition is complete.
  • Erosion and sediment controls, including sediment basin, is complete.
  • The grading permit has been issued.
  • Major earthwork for the gravel parking lot is in process and almost complete.
  • Excavation, installation and back fill of 18 inch reinforced concrete storm pipe is beginning.
  • The geothermal subcontractor is mobilizing. Once the work begins, the installation of the geothermal well field is expected to take about four weeks.
For more information visit the Lovettsville Community Center project page.