Croson Lane Widening - Claiborne Parkway to Old Ryan Road

Overview

  • This project provides for the planning, design, right of way (ROW) acquisition and construction to widen Croson Lane (Route 645) to four lanes between Claiborne Parkway (Route 901) and Mooreview Parkway (Route 2298) and transitioning from four lanes to two lanes from Mooreview Parkway (Route 2298)  to Old Ryan Road (Route 722).
  • The project entails the construction of road widening and lane transitions within a 120-foot right of way and includes the construction of a sidewalk on one side of the road and a shared-use path on the other side.
  • Funding for the project includes Local Tax funding, cash proffers and revenue sharing administered by the Virginia Department of Transportation (VDOT).

Current Phase: Design - 30% Design Plans

 Estimated Timeline

  • Fall 2020 - Winter 2025: Design
  • Fall 2024 - Fall 2025: Right of Way
  • Winter 2025 - Spring 2026: Utilities Relocation 
  • Winter 2026 - Spring 2026: Procurement of Construction Contractor
  • Spring 2026: Award Contract – Construction
  • Spring 2026: Notice to Proceed – Construction
  • Spring 2026 - Fall 2027: Construction
  • Fall 2027: Substantial Completion