Crosstrail Boulevard - Sycolin Road to the Dulles Greenway

Overview

Crosstrail Boulevard from Sycolin Road to the Dulles Greenway (Segment C) project provides for the design, right of way acquisition, utility relocation and the construction of a four-lane median-divided road between Sycolin Road and the Dulles Greenway Interchange. The length of this project is approximately 2,700 linear feet and it includes four-span bridge over the south tributary to Sycolin Creek.

  • Funding for this project is from the Northern Virginia Transportation Authority (NVTA) and local funds.
  • The Commonwealth Transportation Board approved Limited Access Control Change on September 21, 2022. 

Current Phase: Design - Right of Way

Estimated Timeline

  • Fall 2023 - Summer 2024: Right of Way
  • Summer 2024 - Winter 2025: Utilities Relocation 
  • Winter 2025 – Spring 2025: Procurement of Construction Contractor
  • Spring 2025: Award Contract – Construction
  • Spring 2025: Notice to Proceed – Construction
  • Spring 2025 - Spring 2027: Construction
  • Spring 2027: Substantial Completion