This project provides funding to develop a shared-use path, sidewalk, and drainage improvements along the north side of West Colonial Highway (Business Route 7). The shared-use path is proposed to extend from the existing shared-use path near Green Top Drive, just east of Route 287 in the Town of Purcellville, to North Reid Street (Route 1106). The shared-use path will then transition to a sidewalk at North Reid Street and continue to the existing sidewalk east of South Hughes Street (Route 709) in the Town of Hamilton. 

Current Phase: 90% Design

Estimated Timeline

  • Winter 2024: 90% Design Plans Review 
  • Summer 2024: 100% Design Plans Review 
  • Fall 2024 – Fall 2025: Right of Way Acquisition 
  • Fall 2025 – Fall 2026: Relocation of Utilities 
  • Winter 2027 – Spring 2027: Procurement of Construction Contractor 
  • Summer 2027: Award Contract 
  • Fall 2027: Notice to Proceed 
  • Fall 2027 – Fall 2028: Construction Phase Completion 
  • Fall 2028: Substantial Completion 
  1. 1
  2. 2
  3. 3

Stay Informed About This Project

Related Documents

Contact Us

  • If you have questions about this project, email Loudoun County staff or call 703-737-8624.

Media Inquires

  • Email Glen Barbour, Public Information Officer or call 703-771-5086.