Route 15 at Spinks Ferry Road Roundabout

Overview


This project is the second phase of the program of improvements to Route 15 North of Leesburg. This project consists of the design, right-of-way acquisition, utility relocation and construction of a roundabout on Route 15 at Spinks Ferry Road and a realigned Newvalley Church Road.

  • At the December 17, 2019 Board of Supervisor’s (Board) meeting, the Board allocated money to accelerate a portion of the Capital Improvement Project (CIP) to advance the design for this project.
  • Loudoun County provided an update to the Town of Leesburg on Route 15 North Project Improvements, including this Route 15 and Spinks Ferry Road Roundabout project, during the Leesburg Town Council Work Session on April 25, 2022. A video of the meeting and agenda are available for viewing on the Town of Leesburg Webcasts page.
Route 15 at Spinks Ferry Road Overview for Project Page

Current Phase: Design - 90% Design Plans

Estimated Timeline

  • Summer 2021 - Fall 2023: Design
  • Spring 2024 - Spring 2025: Right of Way
  • Winter 2025 - Spring 2025: Utilities Relocation 
  • Summer 2025 - Fall 2025: Procurement of Construction Contractor
  • Fall 2025: Award Contract – Construction
  • Winter 2026: Notice to Proceed – Construction
  • Winter 2026 - Spring 2027: Construction
  • Spring 2027: Substantial Completion

Stay Informed About This Project

Related Documents

Contact Us

Media Inquiries