Current Status: Design - 90% Design Plans
Estimated Timeline
- Fall 2020 - Winter 2024: Design
- Winter 2024 - Spring 2025: Right of Way
- Spring 2025 - Spring 2026: Utilities Relocation
- Summer 2026: Procurement of Construction Contractor
- Fall 2026: Award Contract – Construction
- Fall 2026: Notice to Proceed – Construction
- Fall 2026 - Fall 2028: Construction
- Fall 2028: Substantial Completion