Overview

  • This project provides for the planning, design, right-of-way (ROW) acquisition, and widening of Ryan Road between Evergreen Mills Road (Route 621) and Beaverdam Drive (Route 2475). 
  • Ryan Road will be improved as a Major Collector to suburban, controlled access, four lane, median divided facility with shared use paths on both sides of the road within a 120 foot wide ROW. 
  • This project includes 70% funding from the Northern Virginia Transportation Authority (NVTA).
  • The scope of work also includes modifications at the Evergreen Mills Road intersection to accommodate the four lane roadway.

Virtual Public Meeting

An online meeting was held on April 18, 2024, to provide information about Loudoun County’s Ryan Road Widening project between Evergreen Miills Road (Route 621) and Beaverdam Drive (Route 2475). View the meeting materials and leave a comment below through May 3, 2024.

Meeting Materials

Leave a comment through May 3, 2024:

  • Ryan Road Widening Comment Form - Use this form to submit your comments online.
  • Email us your comments 
  • Mail your comments to:
    Attn: Ryan Road Widening - Kristen Estocsin, Project Manager
    Loudoun County Department of Transportation and Capital Infrastructure
    P.O. Box 7500
    Leesburg, Virginia 20177-7500
  1. 1

Current Phase: Design 30%

Estimated Timeline

  • Winter 2022 – Summer 2025: Design
  • Fall 2025 – Summer 2026: Right of Way Acquisition
  • Summer 2026 - Summer 2027: Utilities Relocation
  • Winter 2027 – Fall 2027: Procurement of Construction Contractor
  • Fall 2027: Award Contract – Construction
  • Fall 2027: Notice to Proceed – Construction
  • Fall 2027 – Fall 2029: Construction
  • Fall 2029: Substantial Completion