Western Loudoun Recreation Complex

Overview

  • This project provides funding for the design and construction of a new 83,000 sq ft recreation center and park on a 142.71 acre site at 36716 Main Street just outside the town limits of Purcellville, Virginia.
    • The recreation center will include meeting/classrooms, administrative office space, gymnasium, kitchen, fitness center, multi-purpose rooms, and a running track. The facility will also include an aquatics center with a competition pool, leisure pool, spa, spectator seating areas, two wet classrooms, splash play area, and associated locker rooms. Additional features on the grounds may include sports courts, rock-climbing wall, outdoor fitness area, and a diving pool.
    • The park will include up to ten athletic fields – four diamond fields and six rectangular fields. Supporting amenities will include athletic field lighting, fencing, public utilities, parking, access from a public road, groundwater wells irrigation, and landscaping. Additionally, the park will include public restrooms, concessions facilities, staff offices, meeting rooms, storage, scorekeeper and umpire areas, a maintenance facility, picnic pavilions, and bleachers. 
    • The project will also provide a master plan identifying a potential future 40,000 square-foot Library facility.
  • The project's current estimated completion date is FY 2028, according to the FY 2024 Adopted Budget
Western Loudoun Recreation Complex

Join us for a public information meeting on Monday, May 6, 2024

Loudoun County invites members of the public to attend a public information meeting on Monday, May 6, 2024, from 6:00 to 7:00 p.m., at the Franklin Park Park Performing and Visual Arts Center, 36441 Blueridge View Lane, Purcellville. Attendees will learn more about the county’s plans for the Western Loudoun Recreation Complex, including including the estimated project schedule, and information on the public input process. Following the presentation, questions about the project will be answered by county staff as time allows. View the promotional meeting flyer (PDF). 

Comments may be submitted at the meeting or by June 1, 2024, via the following:

Current Phase: Design Start

Estimated Timeline

  • Winter 2024: Design Phase begins
  • Fall 2025: 50% design plans
  • Winter 2026: 95% design plans
  • Summer 2026: Park construction begins
  • Fall 2026: Recreation Center construction begins
  • Fall 2028: Construction Phase completion