  • This project provides for the planning, design, right of way acquisition, and construction of a four-lane median divided roadway between Northstar Boulevard and Arcola Boulevard. This project is an extension of Dulles West Boulevard from Dulles Landing Drive (under construction by others) to the intersection of the extension of Northstar Boulevard which is currently under construction. 
  • The proposed roadway consists of a four-lane median divided facility with 10-foot-wide shared use paths on both sides of the road. The project will also include three signalized intersections at Stone Springs Blvd, Arcola Blvd (existing) and Northstar Blvd, in addition it will include utility relocations, two new stormwater facilities and two major culverts crossings. 
  • Coordination with the Northstar Boulevard: Evergreen Mills Road (formerly Shreveport Drive) to Route 50 project has begun and will continue throughout design and construction due to overlap with the Dulles West Boulevard project. More information is provided on the Northstar Boulevard: Evergreen Mills Road to Route 50 project page.
  • Funding for this project includes local source funding and regional Northern Virginia Transportation Authority (NVTA) funds.

Current Phase: Right of Way and Utilities Relocation

Estimated Timeline

  • Winter 2023 - Summer 2024: Right of Way
  • Winter 2023 - Summer 2024: Utilities Relocation 
  • Fall 2024: Procurement of Construction Contractor
  • Summer 2025: Award Contract – Construction
  • Summer 2025: Notice to Proceed – Construction
  • Summer 2025 - Summer 2027: Construction
  • Summer 2027: Substantial Completion