Waterford Mill Stabilization Project Achieves Substantial Completion on July 28

Posted on August 21, 2023 at 12:11 PM by Heidi Kellum

On July 28, 2023, construction to stabilize the historic Waterford Mill in the Village of Waterford reached substantial completion. Over the course of the last nine months, crews completed stabilization work, such as the reconstruction of the historic Hurst frame, window and flooring repairs, structural improvements, painting, interior and exterior masonry work, and excavation and repairs to the water wheel pit.

Over the next few weeks, punch work will be completed, and the mill will be turned back over to the Waterford Foundation for programming. This is the last update for the Waterford Mill Stabilization Project.

For more information, including updated photos, visit the project page.