Design Phase for Farmwell Road Intersection Improvements Set for Fall 2023 Completion

Posted on August 4, 2023 at 9:09 AM by Heidi Kellum

The design phase for the Farmwell Road Intersection Improvements project is currently set to be completed in fall 2023 (October/November/December). The project provides for the design, Right-of-Way (ROW) acquisition, and construction of intersection and pedestrian improvements along the corridor. The project’s ROW phase will begin fall 2023. More information about Loudoun County Capital Project phases is provided at loudoun.gov/capitalprojects.

The Farmwell Road Intersection Improvement project scope includes the addition and/or expansion of turn lanes and receiving lanes at several Farmwell Road intersections, including the intersections at Ashburn Road, Dodge Terrace, Ashburn Village Boulevard, and Smith Switch Road. Pedestrian improvements and connectivity along the corridor, consisting of a shared use path along the south side and a sidewalk along the north side of Farmwell Road, are also part of the project.

Construction of the improvements is currently estimated to begin in 2025.

For more information about the Farmwell Road Intersection Improvements project, visit the project page.


Apr 05

The Design to Improve a Farmwell Road Intersection is Almost Developed

Posted on April 5, 2021 at 9:04 AM by Heidi Kellum

The design to improve a Farmwell Road Intersection, located between Smith Switch Road and Ashburn Road in Ashburn, Virginia, is almost developed. The project provides for the design, Right-of-Way (ROW) and construction of intersection and pedestrian improvements along the corridor. 

In the next quarter, Loudoun County’s design consultant will continue work on the project design, which is almost complete. Major design elements will be presented to the Board of Supervisors for endorsement at their April 20, 2021 Business Meeting. ROW acquisition will follow the completion of the project design and is currently estimated to begin in 2022.

The Farmwell Road Intersection Improvement project scope includes the addition and/or expansion of turn lanes and receiving lanes at several Farmwell Road intersections, including the intersections at Ashburn Road, Dodge Terrace, Ashburn Village Boulevard, and Smith Switch Road. Pedestrian improvements and connectivity along the corridor, consisting of a shared use path along the south side and a sidewalk along the north side of Farmwell Road, are also part of the project scope.

Construction of the improvements is currently estimated to begin in 2023.

For more information about the Farmwell Road Intersection Improvements project, visit the project page.

Nov 18

Revised Design in Process for Farmwell Road Intersection Improvements

Posted on November 18, 2020 at 3:43 PM by Heidi Kellum

The revised design for the Farmwell Road Intersection Improvements project is in process. This quarter, the new plan (at 60% design completion phase) will be submitted to Business and Development (B&D) and the Virginia Department of Transportation (VDOT) for review and comment. Right of way (ROW) acquisition will follow the completion of the design, currently estimated for winter 2021.

This project provides for the design, ROW acquisition and construction of intersection improvements along Farmwell Road between Smith Switch Road and Ashburn Road. The current project scope includes the addition and/or modification of turn lanes and receiving lanes at several Farmwell Road intersections, including Farmwell Road and Ashburn Road, Farmwell Road at Dodge Terrace, Farmwell Road at Ashburn Village Boulevard, and Waxpool Road/Farmwell Road at Smith Switch Road. Pedestrian improvements and connectivity along the corridor are also part of the project scope.

Construction of the improvements is currently estimated to begin in 2023.

For more information about the Farmwell Road Intersection Improvements project, visit the project page.