Design Phase Continues for the Shellhorn Extended Project

Posted on February 14, 2024 at 11:13 AM by Heidi Kellum

Loudoun County continues to work on developing the 100% design plans for Shellhorn Road Extension. This project is partially located on the Dulles International Airport property and requires extensive coordination with the Metropolitan Washington Airports Authority (MWAA). Planning is underway for the utility relocation phase. Due to the extensive coordination, the design phase is estimated to be completed in fall 2024.

The project’s right of way (ROW) phase will begin in fall 2024. More information about Loudoun County Capital Project phases is provided at loudoun.gov/capitalprojects.

This project will extend Shellhorn Road to become a collector road along the north side of the Dulles Greenway. Shellhorn road currently begins in the west at Waxpool Road and ends at Loudoun County Parkway. Shellhorn Road is being extended eastward, parallel to the Dulles Greenway, until it reaches existing Lockridge Road. From there, Shellhorn Road will turn to the south and follow the alignment of Lockridge Road until it reaches the northernmost property line of Dulles Airport. This portion of the Shellhorn Road extension will extend Shellhorn south by the northern entrance to the Loudoun Gateway Silver Line station, then east to connect with the Sterling Blvd. extension. 

The project will also realign a portion of Lockridge Road and extend Randolph Drive to link with Old Ox Road (Route 606). When completed, Shellhorn Road will be a continuous route from Waxpool Road to Route 28 at the present-day Sterling Boulevard interchange. 

For more information about the Shellhorn Road Extended project, including a link to sign up for updates about the project, visit loudoun.gov/shellhornextended.

Jul 21

Design Phase for Shellhorn Road Project Set for Fall 2023 Completion

Posted on July 21, 2023 at 4:26 PM by Heidi Kellum

The Design phase for the Shellhorn Road Extended project is currently set to be completed in fall 2023 (October/November/December). This portion of the Shellhorn Road extension project will extend Shellhorn Road from the northern boundary of the Metropolitan Washington Airports Authority property east to connect with Sterling Boulevard extended. The project’s ROW phase will begin winter 2024. More information about Loudoun County Capital Project phases is provided at loudoun.gov/capitalprojects.

This project will extend Shellhorn Road to become a collector road along the north side of the Dulles Greenway. Shellhorn road currently begins in the west at Waxpool Road and ends at Loudoun County Parkway. Shellhorn Road is being extend eastward, parallel to the Dulles Greenway, until it reaches existing Lockridge Road. From there, Shellhorn Road will turn to the south and follow the alignment of Lockridge Road until it reaches the northernmost property line of Dulles Airport. This portion of the Shellhorn Road extension will extend Shellhorn south by the northern entrance to the Loudoun Gateway Silver Line station, then east to connect with the Sterling Blvd. extension. 

The project will also realign a portion of Lockridge Road and extend Randolph Drive to link with Old Ox Road (Route 606). When completed, Shellhorn Road will be a continuous route from Waxpool Road to Route 28 at the present-day Sterling Boulevard interchange. 

For more information about the Shellhorn Road Extended project, including a link to sign up for updates about the project, visit loudoun.gov/shellhornextended.


Jul 29

Shellhorn Road Extension Comment Period Open

Posted on July 29, 2021 at 9:27 AM by Heidi Kellum

Loudoun County is seeking public comment following an online public meeting on the proposed extension of Shellhorn Road, held on July 26, 2021. Residents are encouraged to visit the project page to review the presentation, watch a recording of the meeting and provide a comment. Comments provided by August 9, 2021, will be shared with the Board of Supervisors at an upcoming Board meeting.

This portion of the Shellhorn Road extension project will extend Shellhorn Road from the northern boundary of the Metropolitan Washington Airports Authority property east to connect with Sterling Boulevard extended. The project will also realign a portion of Lockridge Road and extend Randolph Drive to link with Old Ox Road (Route 606). When completed, Shellhorn Road will be a continuous route from Waxpool Road to Route 28 at the present-day Sterling Boulevard interchange. 

For more information about the Shellhorn Road Extended project, including a link to sign up for updates about the project, visit loudoun.gov/shellhornextended.