Route 9 and 287 Roundabout

Updates on Route 9 and 287 Roundabout. 

Feb 16

Utility Work for the Route 9/287 Roundabout Project Set to Begin in Late February

Posted on February 16, 2024 at 9:20 AM by Heidi Kellum

In late February, utility work will begin as part of the Route 9/287 Roundabout project to construct a roundabout at the intersection of Route 9 and Route 287 near Wheatland. Residents and drivers can expect to see crews clearing trees and working to relocate power and telecommunications utilities near the intersection for the next few months. Although no traffic impacts are planned, heavy equipment may periodically access the roadway. Drivers are advised to take extra caution when traveling through this area and follow all directions from posted signs and road crews. 

The Utilities Relocation phase is currently estimated for completion in March 2025. More information about Loudoun County Capital Projects and phases is provided at loudoun.gov/capitalprojects.

The project consists of a new hybrid roundabout at the intersection of Route 9 and Route 287 with widened roadway approaches. Improvements will also include new drainage, as well as relocation of utilities that will be impacted by the project. When complete, the project will significantly reduce existing traffic congestion, improve safety, and provide a long-term, cost-effective solution for future roadway operation and maintenance. The project is currently estimated for substantial completion in fall 2026.

For more information about the Route 9 and 287 Roundabout project, visit the project page.


Jan 30

Right of Way Activities for Route 9/287 Roundabout Set for Fall 2023 Completion

Posted on January 30, 2024 at 9:19 AM by Shawn Zelman

The Right-of-Way (ROW) phase for the Route 9/287 Roundabout project is currently set to be completed in fall 2023. This project provides for the design, ROW acquisition and construction of a two-lane roundabout at the intersection of Route 9 and Route 287. The project’s Utilities Relocation phase will begin in fall 2023, following the ROW phase. More information about Loudoun County Capital Project phases is provided at loudoun.gov/capitalprojects.

The project consists of a new 2-lane roundabout at the intersection of Route 9 and Route 287 with widened roadway approaches. Improvements will also include new drainage and storm water facilities, as well as relocation of utilities that will be impacted by the project. When complete, the project will significantly reduce existing traffic congestion, improve safety, and provide a long-term, cost-effective solution for future roadway operation and maintenance. The project is currently estimated for substantial completion in fall 2026.

For more information about the Route 9 and 287 Roundabout Project, visit the project page.

Mar 17

Route 9/287 Roundabout Design Plans Submitted for Review and Approval

Posted on March 17, 2021 at 10:43 AM by Heidi Kellum

In January, 100% design plans and floodplain alteration for the Route 9/287 Roundabout project were submitted to Loudoun County Building & Development (B&D) and the Virginia Department of Transportation (VDOT) for review and approval. A design waiver, required for the completion of the project design, was approved by VDOT in December.

The County is currently working on securing nutrient credits for the project, required to satisfy state and local stormwater runoff requirements. Each credit represents a specific amount of absorption of nutrients within a sub-watershed. Virginia’s nutrient trading program is administered by the Department of Environmental Quality (DEQ). 

Construction will follow the completion of ongoing utility coordination and right of way (ROW) acquisition, estimated to begin spring 2021.

The Route 9 and 287 Roundabout project consists of approximately one mile of roadway improvements, including a two-lane roundabout at the intersection of Route 9 and Route 287. Improvements will also include new drainage and storm water facilities, as well as relocation of some utilities. 

When complete, the project will significantly reduce existing traffic congestion, improve safety and provide a long-term, cost-effective solution for future maintenance.

For more information about the Route 9 and 287 Roundabout Project, visit the project page.